Digital analytics report
Elevator Cabin Factory
Q2 2026
report for the production board

Production of premium elevator cabins: profit, capacity, quality, timing

key takeawayMargin is holding, but delays and defects are starting to eat into the effect of line utilization.
Revenue1.84 bln RUB

+8.4% vs plan

Margin24,8%

-0.7 pp vs plan

OEE78,4%

bottleneck: painting

Defects0,72%

above target

Timeline94,1%

parts availability

Lines

Production capacity

91%line A
84%line B
63%painting
72%assembly
18extra cabins
5bottlenecks
11suppliers
94%delivery time
Trend

Revenue and margin

April598 mln RUB24,1%
May621 mln RUB25,0%
June623 mln RUB25,2%
risk

Defects and timelines

0,72%defects
5bottlenecks
94,1%delivery time
quality and supply

Why delivery timelines are becoming risky

5 bottlenecks
quality map

Reasons for defects and rework

0,72%
Painting
34%
Fittings
27%
Geometry
18%
Packaging
11%

The defect share is not critical, but it affects timing: rework uses the same constrained resources as new production.

supply risk

Suppliers keeping the schedule

11critical items
3risk areas
8.4 daysaverage lag
91%parts availability

To increase output, the factory needs not only shop-floor capacity, but also a fittings buffer and painting control before final assembly.

board plan

Decision plan for the production board

DecisionEffectTimelineOwner
14-day fittings bufferminus 2.1 days of waiting2 weeksprocurement
Separate painting slot for reworkqueue reduction1 weekproduction
Daily OEE loopbottleneck visibility3 daysoperations director
Defect control before packaging-0.18 pp defects1 monthquality
forecast

What the 91% scenario gives

+18cabins / quarter
+74 mln RUBEBITDA
-2.4 daysto delivery time

The scenario works only if painting and parts availability do not become the new constraint.